Status of every major project, September 2026
We count a project as real when there's a signed contract and machinery on site. Everything else in the table is an announcement, however official it sounds. Dates change often in Bali, so each row carries its source.
| Project | What it is | Status | Target |
|---|---|---|---|
| Subak Sari–Umalas road | Rp 74 bn link easing Canggu traffic | Under construction since May 12, 2026 | 210 days, about December 2026 |
| Badung undersea water pipe | 7.6 km, about Rp 100 bn | Connected August 5–7, 2026 | Adds about 300 liters a second |
| Gilimanuk–Mengwi toll road | Toll now about 42 km, Pekutatan to Mengwi | Investor tender being prepared | Tender end of 2026, some reports say 2027 |
| Airport–Canggu tram | About 13 km, battery-electric, two phases | Agreement signed September 2026, study under way | Groundbreaking March 2027 |
| Canggu tunnel corridor | Gatot Subroto Barat to Canggu, design changing | Feasibility and financing stage | Main works from 2027 |
| North Bali airport | Second international airport, Buleleng | In the national plan, no site decision | No date |
| Uluwatu traffic scheme | Turn restrictions, 2 pm to 10 pm | Made permanent in July 2026 | In force |
Source: Detik, June 29, 2026; Bali Post, April 7, June 5 and August 4, 2026; Kompas, July 20 and September 22, 2026; Kilas Bali, September 24, 2026; Bali Post, September 22, 2026; Warta Bali, July 2 and September 22, 2026; TheEast, February 17, 2026
The Gilimanuk–Mengwi toll road
The original plan ran 96.84 km along the west coast in three sections, at an estimated Rp 12.7 trillion, with a 2031 opening. It promised to halve the drive from Denpasar to the Gilimanuk ferry port, now about six hours, to three. The first concession never reached financial close, and the government ended it on August 3, 2023.
In August 2026 the scheme changed. The toll section now covers about 42 km, from Pekutatan through Soka to Mengwi, and the stretch from Gilimanuk to Pekutatan becomes a widened national road instead. The province wants the investor tender out by the end of 2026, with the state buying the land once it picks an investor. Planners are recalculating the cost, so the Rp 12.7 trillion figure no longer applies.
For buyers, the road matters most at its eastern end. Mengwi sits just inland from Kedungu and Nyanyi, where land trades well below Badung partly because the roads are slow. That gap could narrow once cars use the toll. But with no investor yet signed, paying for it now means paying for a contract that doesn't exist.
Source: Bisnis.com, April 8, 2026; Bali Post, August 17, 2026; Kompas, July 20 and September 22, 2026; Kilas Bali, September 24, 2026; CNBC Indonesia, May 28, 2024

Choosing an area?
Gusti Ayu will send a short answer on which area fits your plans, on WhatsApp.
Bali LRT is now a tram: the airport–Canggu line
A battery-electric tram has replaced the underground light rail announced in 2024. It would run from Ngurah Rai airport through Kuta, Legian and Seminyak to Canggu. Phase one covers 6.6 km from the airport to Legian. Phase two adds 6.5 km to Canggu.
The province and Badung regency signed with the state railway company in early September 2026. The estimated cost is about Rp 2.2 trillion, pending a feasibility study. The target is groundbreaking in March 2027, phase one running by late 2028 and phase two in early 2031. Other reports give 2028–2029 for the first phase, and the target is 60,000 riders a day.
If it's built, the tram helps the coastal strip from Kuta to Canggu most. We'd count it as a bonus for a villa near a future stop, not as part of the price.
Source: Bali Post, September 22, 2026; Liputan6, September 2026; Periskop, 2026
Canggu: the road under construction and the tunnel on paper
The work you can see is the Subak Sari–Umalas link, a Rp 74 billion contract funded by a regional loan. It started on May 12, 2026 with a 210-day schedule, so expect partial closures on routes between Tibubeneng, Umalas and Kerobokan until around December.
The bigger plan is a corridor from Gatot Subroto Barat in Denpasar to Canggu with a tunnel. In July 2026, officials described a 400 m underpass costing Rp 3.2 trillion, more than Rp 2 trillion of it for land. By September the design had grown to a 2.4 km tunnel within a 3.2 km route, at about Rp 3.5 trillion, or Rp 5 trillion with land, financed by a loan over 2027–2035. Road pricing on the corridor is under discussion. Treat all of this as a design under study.
Land acquisition is the usual bottleneck, and it's where the first toll concession stalled. If a villa you're considering sits near the proposed route, ask the seller whether the plot falls inside the acquisition zone.
Source: Detik, June 29, 2026; Bali Post, July 28, 2026; Warta Bali, September 22, 2026; NusaBali, 2026
The North Bali airport
A second international airport in Buleleng regency is in Indonesia's 2025–2029 national medium-term plan (RPJMN), adopted through Presidential Regulation 12/2025. In July 2026 the central government asked for the project to move faster.
What's missing is the step that makes an airport real. As of September 2026, the Ministry of Transportation hasn't issued a location decision, and no construction has started. Proposals over the years have named several sites, including an offshore concept at Kubutambahan. Until the site is fixed, any "near the new airport" price premium in North Bali is speculation.
Source: Presidential Regulation 12/2025; Kompas, July 21, 2026; TheEast, February 17, 2026; Warta Ekonomi, 2026
Water and power: the constraints buyers ask about
Badung, the regency that covers Canggu, Seminyak and Uluwatu, runs a water deficit of about 1,200 liters a second. The new 7.6 km undersea pipeline came online in early August 2026 and adds about 300 liters a second. That closes only a quarter of the gap. Ask any seller where the villa's water comes from, and whether it has a well or tank as backup.
Power is generally stable, with one recent exception. On May 2, 2025, a fault on the Java–Bali subsea cable blacked out the island for about 12 hours. A villa that lets short-term should budget for a generator or at least a battery backup for the pumps and Wi-Fi.
Source: Bali Post, June 5, June 26 and August 4, 2026; Kompas, May 3, 2025
How we price infrastructure into a villa
"A toll road is coming" is the most common line in west-coast sales decks. It's a real project, but it's a story about the 2030s, and you pay for it today. Roads move prices when cars start using them, not when they're announced, and the gap between the two in Bali is usually years.
There's also a cost in the meantime. A villa 300 meters from a future tunnel may gain value after opening and lose bookings during construction. Guests who came for a quiet villa and got an excavator write reviews, and that hits occupancy faster than it hits price.
- Ask whether the project has a signed concession or contract and financing, not just a budget
- Check the plot against land-acquisition zones
- Run the villa's numbers without the future road, and buy only if they work
- Treat nearby construction as lost bookings
- Confirm the water source and backup, since Badung's deficit is only partly covered
Source: Rise Real Bali valuation practice, 2023–2026
Where this leaves the areas
Canggu and Umalas live with road works into late 2026, but they're also where the only live construction is. Around Uluwatu, the afternoon traffic scheme is now permanent. Kedungu and Nyanyi carry the long-term toll story. If you want to see what's for sale along each of these corridors, browse the catalog by area, or check land prices to see how far the west coast trails Badung today.
What this means for buyers
- Of seven major projects, only two have crews on site: the Subak Sari–Umalas road and the Badung water pipeline.
- In August 2026 the toll road shrank to about 42 km, Pekutatan to Mengwi, and it still has no investor.
- Bali's LRT plan became an airport–Canggu tram, with groundbreaking targeted for March 2027.
- The North Bali airport is in the national plan but has no fixed site and no construction.
- Pay only for infrastructure that exists, and check the plot against acquisition zones.
Next step: Nuanu City in Bali: What It Is and What's Being Built
FAQ
Is Bali getting a toll road?
Not yet. Planners reworked the Gilimanuk–Mengwi toll road in August 2026: the toll section now runs about 42 km from Pekutatan to Mengwi, and Gilimanuk–Pekutatan becomes a widened national road. The province aims to hold the investor tender by the end of 2026 (Kompas, September 22, 2026).
Will Bali have an LRT?
A battery-electric tram has replaced the underground LRT plan. It would run about 13 km from Ngurah Rai airport to Canggu via Kuta, Legian and Seminyak, in two phases. The targets are groundbreaking in March 2027 and a first phase running by late 2028 (Bali Post, September 22, 2026).
Has construction started on the North Bali airport?
No. It's in the 2025–2029 national medium-term plan under Presidential Regulation 12/2025, but as of September 2026 the transport ministry hasn't issued a location decision, and construction hasn't started.
What road works are there in Canggu in 2026?
The Rp 74 billion Subak Sari–Umalas link has been under construction since May 12, 2026, on a 210-day schedule. A larger Gatot Subroto Barat–Canggu corridor with a tunnel is in feasibility, with main works planned from 2027.
Does Bali have water shortages?
Badung regency runs a deficit of about 1,200 liters a second. A 7.6 km undersea pipeline connected in August 2026 adds about 300 liters a second, so villas should keep a well or storage tank as backup.
How we know this
Each project's status comes from dated reports in Indonesian and English media, listed under every section. We record a project as under construction only when reports show a contract and site work, and keep announced dates in the target column. Where sources disagree, as on the toll tender date and the tram's first-phase opening, we give both. The toll road's cost and opening year belong to the old 96.84 km scheme, and planners are recalculating them for the shorter one. The Canggu tunnel's design changed between July and September 2026, and we report both versions. Our view on how infrastructure affects prices is judgment from practice, not a calculation.
- Detik, Subak Sari–Umalas road, June 29, 2026
- Bali Post, toll road scheme, August 17, 2026; tram, September 22, 2026; Canggu corridor, July 28, 2026; water, April 7, June 5, June 26 and August 4, 2026
- Kompas, toll road tender and route, July 20 and September 22, 2026; North Bali airport, July 21, 2026; blackout, May 3, 2025
- Kilas Bali, toll road tender, September 24, 2026; Bisnis.com, April 8, 2026
- Warta Bali, Canggu tunnel, September 22, 2026; Uluwatu traffic scheme, July 2, 2026
- Liputan6, airport–Canggu tram, September 2026
- TheEast, North Bali airport, February 17, 2026; Presidential Regulation 12/2025
- NusaBali, Ngurah Rai passengers 2025, January 2026
- Rise Real Bali valuation practice, 2023–2026
By Dmitrii Rogov, Rise Real Bali.
Rise Real Bali is a real estate agency in Bali. We write from the deals we handle and from public data, and we name our sources.
This report is published under the CC BY 4.0 license. You may quote, republish and use the figures and text commercially if you credit "Rise Real Bali", name the license and link to this page. Photos and renderings are not covered by the license: their rights belong to the developers and other rights holders.